Field study on the ultimate bearing capacity of enlarged grout base of pre-bored grouted planted pile

WANG Wei-dong1, WANG Meng2, WU Jiang-bin2   

  1. 1. Arcplus Group PLC, Shanghai 200011, China 2. Underground Space & Engineering Design & Research Institute, East China Architecture Design & Research Institute Co., Ltd., Shanghai 200011, China
  • Online:2023-11-10 Published:2024-02-02
  • Contact: WANG Meng, male, born in 1991, PhD, mainly engaged in the design and theoretical research of foundation and foundation pit engineering. E-mail: wangm1028@126.com E-mail:weidong_wang@ecadi.com.
  • About author:WANG Wei-dong, male, born in 1969, PhD, National Great Engineering Survey Design Master, Professorate Senior Engineer, PhD supervisor, mainly engaged in the design and theoretical research of underground engineering, deep foundation pit engineering, and high-rise building foundation.
  • Supported by:
    the Shanghai Science and Technology Development Funds (22dz1202900, 22QB1400500).

Abstract: Pre-bored grouted planted pile is a new type of eco-friendly pile foundation. The combination of the lower section of PHC nodular pile and the pile base expansion greatly improves the vertical bearing capacity of single pile. A lot of application practices have been achieved in Jiangsu, Zhejiang and Shanghai regions, but limited to the current research status, the bearing capacity of enlarged grout base is not clear. Based on the in-situ self-balanced loading test, the ultimate compressive bearing capacity of the enlarged grout base of the pre-bored grouted planted pile is investigated. The research results reveal that the measured ultimate bearing capacity of the enlarged grout base of the pile is 40% higher than that calculated by the specifications. The back analysis of the test results shows that the ultimate end resistance reduction coefficient of Shanghai ⑦ layer of silt is 0.72-0.81, which is significantly higher than the recommended value of 0.50-0.55 in the specifications. The bearing capacity of the enlarged grout base of the pile is mainly controlled by the end bearing capacity, and the required displacement value for its full bearing capacity is about 0.03 times the pile diameters. The enlarged grout base of the pile accounts for 64% to 67% of the bearing capacity of pre-bored grouted planted pile, and the structural integrity of the enlarged grout base plays a key role in the working performance of the pre-bored grouted planted pile.

Key words: pre-bored grouted planted pile, enlarged grout base, self-balanced loading test, bearing capacity, end resistance of pile